|
|
|
|
PUC Directs EDCs To Procure Longer Default Service Product, Use Capacity Proxy Price
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
The Public Utilities Commission of Ohio today issued orders concerning separate requests from the FirstEnergy EDCs, and AEP Ohio, for interim relief to conduct default service auctions for supply for the period beginning June 1, 2024 while the respective EDCs' proposed new electric security plans governing default service remain pending before PUCO
With respect to the FirstEnergy EDCs, PUCO denied the FirstEnergy EDCs' request to hold two separate auctions, approximately in early February and early April, respectively, in which 100% of load for the 12-month period June 1, 2024 to May 31, 2025 would have been procured solely through 12-month products (50% each auction)
The FirstEnergy EDCs had proposed the use of only 12-month products due to the lack of a PJM auction capacity price beyond May 31, 2025 (the FirstEnergy EDCs' request was filed the same day PUCO generically directed EDCs to resume longer-term SSO products via capacity proxy price).
For the FirstEnergy EDCs, PUCO instead ordered that 50% of the load should be procured under a 24-month product, with a capacity proxy price used for the 24-month product
"[W]e authorize FirstEnergy to conduct two auctions
to procure 50 tranches of 12-month product and 50 tranches of 24-month product, which
should utilize a capacity proxy price as authorized by the Auction Order [PUCO's recent capacity proxy price order]," PUCO said
PUCO still authorized the FirstEnergy EDCs to conduct two auctions (rather than one auction for both products); PUCO did not specify during which specific auction each product should be procured
"We ... note
that utilizing various product lengths helps reduce price volatility," PUCO said
PUCO's order was limited to the conduct of the interim auctions and did not address or pre-judge the pending ESP application of the FirstEnergy EDCs, or any terms thereunder
In contrast, PUCO granted interim relief to AEP Ohio to allow AEP Ohio to procure the remaining 50% of supply for the 12-month period starting June 1, 2024 via only a 12-month product.
In approving the use of a 12-month product for AEP Ohio's March 2024 auction, PUCO's order states, "we acknowledge
that AEP Ohio’s November 2023 auction incorporated a mix of products."
However, while AEP Ohio initially received, in September 2023, interim relief to procure both 12- and 24-month products in the November 2023 auction, PUCO's order approving the November 2023 auction results, as well as a post-auction report from the auction manager, indicate that only a 12-month product was procured in November 2023, with 50 tranches produced under a 12-month product with a term of June 1, 2024 to May 31, 2025
In any case, PUCO said as follows in permitting AEP Ohio to procure only a 12-month product in the March 2024 auction: "AEP Ohio is authorized to
conduct an SSO auction in March 2024, consistent with the provisions of its current ESP.
The Commission strongly encourages AEP Ohio to procure generation supply products of
various lengths in subsequent auctions to reduce price volatility; however, we acknowledge
that AEP Ohio’s November 2023 auction incorporated a mix of products and, for that reason,
we will not alter the Company’s request to offer only a 12-month product. In response to
Constellation’s comments, we note that AEP Ohio has not only committed to a capacity
proxy mechanism in its pending ESP proceeding, but the Company, as well as all other
EDUs operating within Ohio, have been directed to develop appropriate CPP mechanisms
with their respective auction managers for auctions that contain products for delivery years
in which the capacity price remains unknown. CPP Order at ¶ 35. Notwithstanding this
instruction, we recognize that the capacity price is known through May 31, 2025. As such,
requiring a capacity proxy mechanism to be implemented prior to AEP Ohio’s March 2024
auction, which is limited to 12-month products, will not be necessary; however, we fully
expect AEP Ohio to adhere to our directives contained in the CPP Order for future SSO
auctions. For these reasons, the Commission grants AEP Ohio’s motion for interim relief."
PUCO's order was limited to the conduct of the interim auctions and did not address or pre-judge the pending ESP application of AEP Ohio, or any terms thereunder
Also, as is customary, PUCO's order concerning both utilities included language similar to the following: "As a final matter, the Commission notes that we reserve the right to review
and modify any feature of the SSO auction process, as the Commission deems necessary
based upon our continuing oversight of the process, including any reports on the auctions
provided to the Commission by the independent auction manager, AEP Ohio, Staff, or any
consultant retained by the Commission."
CASE NO. 23-23-EL-SSO
CASE NO. 23-301-EL-SSO
ADVERTISEMENT ADVERTISEMENT Copyright 2010-23 Energy Choice Matters. If you wish to share this story, please
email or post the website link; unauthorized copying, retransmission, or republication
prohibited.
Allows Another EDC To Procure Only 12-Month Product
January 10, 2024
Email This Story
Copyright 2010-23 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW! -- Customer Care Specialist I & II- remote/hybrid -- Retail Supplier
• NEW! -- Pricing Analyst - Retail Power
• NEW! -- Electricity Pricing Analyst
-- Retail Supplier
• Business Development Manager -- Retail Supplier
• Call Center Manager -- Retail Supplier
|
|
|