Texas PUC Designates ERCOT Winter Capacity RFP As Interim Solution Subject To PURA Cost Cap
The following story is brought free of charge to readers by VertexOne, the exclusive EDI provider of EnergyChoiceMatters.com
In a vote today, the Texas PUC has designated ERCOT's winter capacity RFP as an interim solution under PURA § 39.1594(a)(1).
This means that costs under the winter capacity RFP will be included in the total capped cost of any performance credit mechanism
As previously reported, ERCOT developed a confidential budget for the winter capacity RFP, but did not file it publicly, expressing concerns that bidders could exploit the information to bid right at the cap
Texas PUC Commissioner Will McAdams also said that the PUC will need to allow retail electric providers to pass-through costs under the winter RFP to customers on fixed rate contracts
The retail market cannot absorb that type of unexpected cost on short notice, McAdams said of the winter capacity RFP costs
ADVERTISEMENT ADVERTISEMENT Copyright 2010-23 Energy Choice Matters. If you wish to share this story, please
email or post the website link; unauthorized copying, retransmission, or republication
prohibited.
McAdams Says That PUC Will Need To Allow REPs To Pass-Through RFP Costs To Fixed Rate Customers, Says Retail Market Can't Absorb Such Unexpected Costs
November 2, 2023
Email This Story
Copyright 2010-23 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com
NEW Jobs on RetailEnergyJobs.com:
• NEW! -- Customer Care Specialist I & II- remote/hybrid -- Retail Supplier
• NEW! -- Pricing Analyst - Retail Power
• NEW! -- Electricity Pricing Analyst
-- Retail Supplier
• Business Development Manager -- Retail Supplier
• Call Center Manager -- Retail Supplier
|
|
|