Texas PUC Chair Proposes Electricity Relief Program That Would Reimburse Retail Electric Providers, At Standard Rate, For Unpaid Bills Due To Disconnect Moratorium During COVID-19 Emergency

Program To Be Funded Via New TDU Rider Applicable To All Customer Classes


March 24, 2020

Email This Story
Copyright 2010-20 EnergyChoiceMatters.com
Reporting by Paul Ring • ring@energychoicematters.com

The following story is brought free of charge to readers by EC Infosystems, the exclusive EDI provider of EnergyChoiceMatters.com

Texas PUC Chairman DeAnn Walker has proposed for consideration at the PUC's upcoming open meeting an Electricity Relief Program that would reimburse retail electric providers for energy charges associated with providing continuity of service to residential customers during a disconnection moratorium during the COVID-19 Emergency

Disbursements to REPs would be calculated using a standardized energy charge based on an average energy cost of $0.04 per kWh. REPs would cease being charged delivery charges for affected customers

The program would be funded by a new TDU rider equal to $0.65 per megawatt hour (MWh) applicable to all customer classes

The proposal, whose details are below, recognizes that further details of the COVID-19 Electricity Relief Program will need to be addressed in the coming days and the plan will need to be supplemented and may need to be modified.

Walker also proposes other measures related to late payment fees and deferred payment plans noted further below

As proposed, the Electricity Relief Program provides as follows:

During the duration of Governor Abbott's COVID-19 Disaster Declaration and any extensions, the Commission authorizes creation of a customer assistance program for residential customers meeting eligibility criteria approved by the Commission (COVID-19 Electricity Relief Program).

The COVID-19 Electricity Relief Program creates a temporary exemption from disconnections for non-payment for eligible residential customers in areas open to customer choice, thus protecting affected residential customers and reducing the exposure of the competitive market from excessive COVID-19-related bad debt that could lead to industry upheaval and bankruptcies.

Only the residential classes will be eligible for the COVID-19 Electricity Relief Program and suspension of disconnection for non-payment. Retail electric providers (REPs) will contact residential customers to place the customer on deferred payment plans before submitting reimbursement claims.

The Commission will issue an order under 16 Texas Administrative Code (TAC) §§ 25.480(j)(1)(B) and 25.498(i)(1)(B) requiring REPs to offer deferred payment plans to customers who have experienced financial hardship due to the state of disaster Governor Abbott has declared for COVID-19. As provided by those rules, REPs may implement switch-holds for customers who enter into a deferred payment plan. When a customer contacts a REP and indicates an inability to pay a bill, or to make a deferred payment plan installment, the REP will inform the customer of the COVID-19 Electricity Relief Program and will provide instructions for the customer to contact the Low-Income List Administrator (LILA) to self-enroll.

The moratorium on disconnections for non-payment currently implemented by the transmission and distribution utilities (TDUs) will end upon the implementation of the COVID-19 Electricity Relief Program as described below.

TDUs will implement a rider to facilitate funding the COVID-19 Electricity Relief Program for customers within the customer choice areas of the Electric Reliability Council of Texas (ERCOT). The rider will collect funds to be utilized to reimburse TDUs and REPs for unpaid bills from eligible residential customers experiencing unemployment due to the impacts of COVID-19 and to ensure continuity of electric service for those residential customers.

The rider will be a set amount per kilowatt hour ("kWh") with funds collected and administered by the TDUs across all customer classes. The initial rider will be based on $0.65 per megawatt hour (MWh). The TDUs will implement the rider within ten days of the Commission's order establishing the COVID-19 Electricity Relief Program. The rider will have an immediate effective date.

For the initial balance of the fund, each TDU will verify the amount it needs based upon estimated reimbursement requests. ERCOT will provide the initial contribution of up to a total of $15 million to create the TDUs' initial fund balance from the cash reserves that it has for implementation of the real-time co-optimization project. Each TDU must repay ERCOT for the initial balance contributions received from ERCOT. Amounts to be repaid to ERCOT will be collected through the TDU riders and repaid prior to the end of the COVID-19 Electricity Relief Program.

If the rider is collecting insufficient funds to cover the TDU and REP eligible costs, then the TDU will file a request for an adjustment to the rider. At any point during the pendency of the COVID-19 Electricity Relief Program, TDUs or REPs may petition the Commission for a review of or amendment to the COVID-19 Electricity Relief Program, including adjustments to the rider. The Commission will act on any petition within 30 days.

The fund will reimburse the following entities and eligible costs: REPs with energy charges related to eligible residential customers with an unpaid, past due electric bill subject to a disconnection for non-payment notice; TDUs for delivery charges related to eligible residential customers with an unpaid, past due electric bill subject to a disconnection for non-payment notice; the third-party administrator to cover its reasonable costs of administrating the COVID-19 Electricity Relief Program eligibility process; and ERCOT for the initial contribution.

Disbursements to REPs will be calculated using a standardized energy charge based on an average energy cost of $0.04 per kWh.

The following customer identification process will be used, facilitated by the third-party vendor, who is the same entity as the Low-Income List Administrator (LILA). A residential customer who cannot pay their electric bill due to unemployment or low-income from the effects of the COVID-19 disaster must contact the LILA. The residential customer must provide the LILA with an attestation of unemployment (to be followed by documentation of unemployment within 30 days) and sufficient information to identify the customer's electric service account (e.g., service address, account number, and telephone number). The LILA will compare the customer's information to the lists of residential customers submitted by REPs to create files of matching residential customers eligible for the COVID-19 Electricity Relief Program. Each REP must retrieve from the third-party vendor the list of residential customers served by that REP who are eligible for the COVID-19 Electricity Relief Program.

REPs will cease submitting disconnection for non-payment orders for residential customers identified as eligible for the COVID-19 Electricity Relief Program.

A residential customer who demonstrates eligibility for the COVID-19 Electricity Relief Program is deemed as having established satisfactory credit for the purpose of 16 TAC § 25.478(a).

TDUs will cease charging REPs for delivery charges related to customers identified as eligible for the COVID-19 Electricity Relief Program.

The suspension of disconnections for non-payment and addition of residential customers to the COVID-19 Electricity Relief Program will end six months after implementation unless extended by the Commission. If the disaster declaration has not been lifted at the end of the six-month period, the COVID-19 Electricity Relief Program may be extended for an additional period based upon a reassessment of the need for the COVID-19 Electricity Relief Program by the Commission and based upon the status of the disaster declaration. The riders will remain in place and reimbursements to the TDUs and REPs will continue after the COVID-19 Electricity Relief Program has otherwise ended to complete any remaining COVID-19 Electricity Relief Program cost recovery and to disburse all reimbursement amounts or remaining balances.

Final claims for reimbursement must be submitted to TDUs not later than 90 days after the end of the COVID-19 Electricity Relief Program. For any amounts recovered under the rider that remain after the end of the COVID-19 Electricity Relief Program, the TDUs will issue a refund through REPs to end-use customers in the same manner the rider was charged. REPs must pass through any monies refunded to customers.

TDUs will prepare reports on the COVID-19 Electricity Relief Program to be filed at the Commission every 30 days providing data showing aggregate amounts of reimbursements to the TDUs and REPs. Reimbursements and collections will be subject to reconciliation and audit by the Commission.

REPs will submit one spreadsheet with reimbursement claims to TDUs monthly on the 15th of each month. TDUs will create a standard spreadsheet format; however, the spreadsheet will include the following information: ESI IDs; kWh usage; kWh usage x $0.04; and Invoice Number. Reimbursement payments to REPs will be processed within 14 days.

REPs will reflect reimbursement sought through the COVID-19 Electricity Relief Program on the affected customer's account and cease to seek continued collection where funds are received from the program.

The Commission will waive all relevant deadlines within its rules related to required changes to the REP's Terms of Service and Electricity Facts Labels contract documents relevant to the COVID-19 Electricity Relief Program.

The Commission will issue an order granting authority for the TDUs to create a regulatory asset to capture all reimbursement amounts and the ERCOT contribution. The funds collected from the rider will be used to offset the regulatory asset and the ERCOT contribution repayment. The rider will stay in effect until the regulatory asset balance is zero and ERCOT has been reimbursed.

Walker also proposes that the PUC grant an exception to 16 TAC § 25.480(c), which relates to assessment of late fees on customers for delinquent bills.

Walker also recommends that the Commission issue an order, as provided by 16 Texas Administrative Code (TAC) §§ 25.480(j)(1)(B) and 25.498(i)(1)(B), directing retail electric providers to offer a deferred payment plan to customers, upon request.

Docket 50664

ADVERTISEMENT
NEW Jobs on RetailEnergyJobs.com:
NEW! -- Energy Procurement Manager
NEW! -- Channel Relations Manager -- Retail Supplier
NEW! -- Senior Retail Energy Markets Pricing Analyst
NEW! -- Energy Market Analyst -- DFW
Senior Consultant - Competitive Energy Markets -- Houston

Email This Story

HOME

Copyright 2010-20 Energy Choice Matters.  If you wish to share this story, please email or post the website link; unauthorized copying, retransmission, or republication prohibited.

 

Archive

Daily Email

Events

 

 

 

About/Contact

Search