Live Blog |
Search |
Calif. Staff Reports on Implementation of Direct Access Re-
July 15, 2011
Email
This Story
Some 26,000 requests for direct access were rejected in California's
Phase III of the process to implement the expanded direct access cap, according to
a PUC Staff report detailing results of the Year 2 and Year 3 Notice of Intent
periods (R.07-
Accepted and rejected notices during each period are below:
Year 2, Notices submitted July 16, 2010 for service starting Jan. 2011
Year 3, Notices submitted Jan. 31, 2011 for service starting Jan. 2012
Load data in annual GWh. The totals shown for rejected notices exclude duplicate notices already accepted.
The Staff report also confirms that the caps were essentially hit immediately in each of phases, as previously reported:
Furthermore, Staff found that the utilities have occasionally accepted new load after the applicable cap for a specific phase was hit, either due to lower usage opening up room under the cap, or to correct errors.
For example, Pacific Gas & Electric, in mid-
The utilities have adjusted upward or downward the amount of load they accept based on available room under the cap (see chart at bottom). For example, the total annual GWh load SCE accepted for Year 2 and Year 3 were both greater than the respective annual allotments of direct access load. Specifically SCE explained that it accepted the additional load in January 2011, "as a result of reduced usage by DA customers and returns to bundled service by some DA customers, as well as some customers with accepted Six Month Notices ultimately not switching to DA, all of which freed up additional space under the existing load limit."
PG&E also explained a processing error that resulted in its load by the end of last year exceeding the cap. The error involved load of customers whose notices were accepted, given an erroneous computation of the customers' load. A customer inquiry uncovered the error. PG&E then performed a wider investigation covering all service accounts [SAs] contained in accepted customer notices and determined that other SAs from other customers should also have been accepted. The additional acceptance of these SAs brought PG&E's acceptances to slightly over the limit set in the tariff for this phase of direct access reopening.
Staff directed that the utility's web pages regarding the cap must be updated at least monthly so customers can see whether room is becoming available under the cap, and that the web page must show the last update date. If room becomes available under the current (Year 2) cap, the utilities are required to notify customers on their web pages, Staff said.
As of the Staff report, all utility web pages state that they are not currently accepting
notices. Looking at utility web pages in mid-
|
Accepted Customers |
Accepted Load |
Rejected Notices |
PG&E |
200 |
1,593 |
5,241 |
SCE |
375 |
1,810 |
8,997 |
SDG&E |
37 |
156 |
1,928 |
Total |
612 |
3,559 |
16,166 |
|
Accepted Customers |
Accepted Load |
Rejected Notices |
PG&E |
66 |
605 |
14,288 |
SCE |
83 |
869 |
8,617 |
SDG&E |
21 |
113 |
3,113 |
Total |
170 |
1,587 |
26,018 |
Time Cap Hit |
2011 Cap (min/sec) |
2012 Cap (min/sec) |
PG&E |
2/21 |
0/5 |
SCE |
0/57 |
0/47 |
SDG&E |
0/7 |
0/18 |
$
Enrollment Information |
|
|
|
|
| ||
Unless otherwise specified, such as "customers," all units are Annual GWh. | |||||||
|
|
|
|
|
Room Under Cap | ||
Line |
PG&E |
SCE |
SDG&E |
PG&E |
SCE |
SDG&E | |
1 |
Load Cap |
9,520 |
11,710 |
3,562 |
|
|
|
2 |
DA Base Line Load |
5,574 |
7,765 |
3,100 |
|
|
|
3 |
30Apr2010 Load |
5,498 |
7,554 |
3,056 |
|
|
|
4 |
Load of Existing DA Eligible customers w/6- |
569 |
6 |
0 |
|
|
|
5 |
SB 695 DA Load Allowance |
3,946 |
3,946 |
462 |
|
|
|
6 |
Y1 Incremental = DA Allowance x 0.35 |
1,381 |
1,381 |
162 |
|
|
|
7 |
Y1 Accepted Load |
1,008 |
1,583 |
174 |
373 |
- |
- |
8 |
Y1 Annual Cap |
6,955 |
9,145 |
3,262 |
|
|
|
9 |
31Jul 2010 Load |
6,296 |
8,255 |
3,227 |
659 |
890 |
35 |
10 |
31Aug2010 Load |
6,486 |
8,579 |
3,233 |
469 |
566 |
29 |
11 |
31Dec2010 Load |
6,967 |
7,747 |
3,231 |
- |
1,398 |
30 |
12 |
Y2 Incremental = New DA Allowance x 0.35 |
1,381 |
1,381 |
162 |
|
|
|
13 |
Y2 Accepted Load |
1,593 |
1,810 |
156 |
|
|
|
14 |
Y1+Y2 Accepted Load |
3,170 |
3,399 |
330 |
14.77% |
23.08% |
2.04% |
15 |
Y1+Y2 Allowance |
2,762 |
2,762 |
323 |
|
|
|
16 |
Y2 Annual Cap |
8,336 |
10,526 |
3,423 |
|
|
|
17 |
31Jan2011 Load |
7,579 |
8,972 |
3,370 |
757 |
1,555 |
53 |
18 |
30April2011 Load |
8,545 |
10,141 |
3,341 |
- |
385 |
82 |
19 |
31May2011 Load |
8,546 |
10,119 |
3,328 |
- |
407 |
95 |
20 |
30 June 2011 Load |
8,516 |
10,109 |
3,317 |
- |
417 |
106 |
21 |
Y3 Incremental = New DA Allowance x 0.20 |
789 |
789 |
92 |
|
|
|
22 |
Y3 Accepted Load |
605 |
869 |
113 |
|
|
|
23 |
Y3 Annual Cap |
9,125 |
11,315 |
3,516 |
|
|
|
24 |
Total Accepted DA Load post 15 Mar 2010 |
3,775 |
4,268 |
443 |
|
|
|
25 |
DA Load Allowance Less Total Accepted DA Load post 15 Mar 2010 |
171 |
- |
19 |
|
|
|
Notes: |
|
|
|
|
|
| |
The SB 695 Load Cap (line 1), Base Line DA (line 2), and the DA load allowance (line
5) are taken from Appendix 1 of D.03- |
| ||||||
SCE's baseline equals the annual DA load in its service territory as of November
30, 2009, plus Cerritos' set- |